Planning & Development

Chair: Gabriel de Varennes, info@overbrook.ca

Committee Members: Carol Christensen, Wendy Dennys, Henrieta Detcheva, Gabriel de Varennes, Steve McNamee.

Meetings: The Committee meets on the second Tuesday of each month, at 7:30 pm at the Overbrook Community Centre. The meetings are “open” and members of the community are welcome to attend.

What do we do?

  • Represent the best interests of the Overbrook community in consultations with the City of Ottawa Planning and Growth Management Department, developers and their representatives.
  • Participate in initiatives, studies and exercises that the City of Ottawa Planning and Growth Management Department may undertake.
  • On behalf of the community, respond to applications for development, variances or rezoning in Overbrook in order to achieve the best and most compatible results for our neighbourhood.

In 2015, our plan is to:

  • in co-operation with our Ward 13 Councillor, campaign for the City of Ottawa to consult with the Overbrook community and establish a Community Design Plan that will help to guide the future development of our community in a cohesive manner.
  • continue to represent community interests in response to development applications and through participation in city planning initiatives.

Current Activities:

Developments currently actively under review by the OCA are listed below:

1111 North River Road

Current Status of Development:

September 12, 2013 – A public meeting was held for residents to review the plans.

February 11, 2014 – Developers present Zoning Bylaw Amendment to City Planning Committee.

February 2015: Construction underway.

October 2015: Construction complete.

____________________________________________________________________________________________

1123 North River Road / 2-A West Presland

Current Status of Development:

January 2014: The building has been demolished for a number of years now.

November 2014: New plans were submitted for the site to build one detached home and two semi-detached homes.

December 2014:  The Committee of Adjustment approved the developer’s application for severances and for 16 variances for relief from Zoning By-laws.

August 2015: The Committee of Adjustment approved changes to the plan for this unit.

____________________________________________________________________________________________

251 Glynn Avenue

The developer plans to build three townhouses on this property.

February 4, 2015: The Committee of Adjustment approved the developer’s application for severances of this property.  The OCA Planning and Development Committee supported this application.

August 2015: Construction underway.

_____________________________________________________________________________________________

106 Ontario Street

The developer plans to build three townhouses on this property..

Current Status of Development:

January 16: Public meeting to meet developer and city planner at Overbrook Community Centre, 6 to 7 pm

February 2015: Construction underway.

July 2015: Construction complete.

_____________________________________________________________________________________________

1 King George Street

The developer plans to demolish the existing building and build two duplexes on this property.

February 18, 2015:  The Committee of Adjustment adjourned the developer’s application for severances and for 20 variances from the zoning by-laws, first, until April 1 and, then, until May 20, and again until June 17 to allow time for the developer and the community to work towards agreement on a development acceptable to all.

July 2015: The Committee of Adjustment denied the developer’s application for variances and severance.

September 2015: The developer is revising the plans for this project. One semi-detached dwelling is contemplated for this property.

_____________________________________________________________________________________________

131 Queen Mary Street

The developer plans to demolish the existing one-storey detached dwelling and construct a three-storey semi-detached dwelling.

On May 6, 2015, the Committee of Adjustment approved the developer’s application for severance and for five variances from the Zoning By-law.

The OCA Planning and Development Committee supported this application.

_____________________________________________________________________________________________

228 Glynn Avenue

The developer plans to demolish the existing dwelling and construct a two-storey semi-detached dwelling.

On May 6, 2015, the Committee of Adjustment approved the developer’s application for severance and for two variances from the Zoning By-law.

The OCA Planning and Development Committee supported this application.

_____________________________________________________________________________________________

317 Glynn Avenue

August 2015: The Committee of Adjustment approved the application to sever the property and for minor variances to permit the demolition of the existing dwelling and the construction of one semi-detached dwelling. The OCA Planning and Development Committee supported this application.